Tunnel drill in Berlin assembled by Liebherr LR 1600/2 crane from Riga Mainz

LR1600-2-Riga-Mainz
Click to enlarge

There is a gap of around two kilometers in Berlin’s underground network between the current stations at “Alexanderplatz” and “Brandenburger Tor”. The first trains are due to start running on this section directly beneath the historic city center in 2019. A tunel drill measuring 74 meters in length and weighing in at 700 tons has now been assembled in the enormous construction shaft near the Red City Hall to excavate the first tunnels. The Herrenknecht drill was delivered in individual components to the site on barges sailing up the River Spree. A brand new Liebherr LR 1600/2 crawler crane from Riga Mainz took care of the unloading and hoisting work.

LR1600-2-Riga-Mainz-2
Click to enlarge

After around one week of preparation the red crawler crane was ready for use on the river bank with its 72 m lattice boom and ballast trailer. The LR 1600/2 hoisted the individual components of the tunnel drill on to land during two night shifts from the edge of a temporary dock specially created for site logistics purposes. The heavyweight cargo had to be unloaded at night on this section of river since it is extremely busy with excursion boats during the day.

“Resetting, removing and refitting the ballast on a ballast pallet would have taken longer than the actual 14 hoisting cycles to move the components”
– Uwe Langer, Riga Mainz

Uwe Langer, boss of the Mainz-based crane specialists, ordered his new 600-tonne crane from the Liebherr Plant in Ehingen with a ballast trailer. The heavy duty crane was able to exploit the features of this optional equipment in full in this, its first site operation. For each hoisting cycle the crane had to travel backwards around 30 meters and then slewed through 120° to lower the load. “Resetting, removing and refitting the ballast on a ballast pallet would have taken longer than the actual 14 hoisting cycles to move the components”, says Langer.

The counter weight (in this case 350 tons) can be left on the ballast trailer even when the load is not being hoisted. The crawler crane travels and slews on 12 giant wheels. The various components of the tunnel drill were lowered 20 meters down into the construction trench by the LR 1600/2 over a period of two weeks. The heaviest machine components, the front plate, weighed in at 135 tons.

Tags

Liebherr

Liebherr is the biggest crane manufacturer in the wold. The news messages and press releases under this profile are sent to us by Liebherr and placed by CraneMag. Sometimes the news is shortened or rewritten, but the subjects aren't changed. When CraneMag writes an own post about Liebherr, this will be posted under our own profile.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *