Reinforcement cages to 40 m depth: a telescopic crawler crane on France’s biggest water project
On the Haliotis 2 wastewater scheme in Nice, a Sennebogen 6113 E telescopic crawler crane is placing reinforcement cages into 82 stabilising barrettes sunk to 40 metres along the seaward dike.
Earthquake protection for a €700m plant
Haliotis 2, between the Promenade des Anglais and the runways of Nice Côte d’Azur airport, is one of the largest water treatment projects currently under way in France, representing roughly €700 million including construction and operation. Before the treatment structures can be built, the existing dike has to be underpinned. On the seaward side, 82 stabilising barrettes are being installed along some 500 metres of dike to prevent slope failure in an earthquake. FAYAT Fondations holds the contract for this work.
Cages of 6.5 m width, 40 m deep
The barrettes are built using diaphragm wall technique. Each panel is excavated with a grab and desanded, then a purpose-made reinforcing steel cage is lowered in and the element concreted at depths of up to 40 metres. Individual elements measure roughly 6.5 to 6.6 metres wide with a wall thickness of 800 mm.
The lifting is handled by a Sennebogen 6113 E telescopic crawler crane supplied by SAML, a subcontractor of the FAYAT Group. Cages are picked up horizontally, brought upright and then threaded into the prepared excavation. Because the crane can travel with a suspended load and telescope under load, and offers full capacity through 360 degrees, cages can be walked into position in tight working space without the slew angle dictating what the crane can hold.
“On this site in particular, the simultaneous control of all movements is crucial. We can operate the undercarriage, upper structure, and boom movement at the same time without setting down the load. This makes positioning the reinforcement cages significantly easier.”
— Gilles Cortes, foreman and crane operator
Extraction loads on the boom
The 6113 E is not confined to cage work. It also installs and extracts casing and handles equipment during borehole desanding. Extraction in particular puts high dynamic loads into the machine and boom, which is where the crawler undercarriage and the boom’s structural design earn their place; the crane has to stay stable and precisely controllable through repeated cycles rather than single peak lifts.
For the contractor the appeal is a single machine covering cage handling, casing work and general site lifting on a confined coastal site, avoiding the outrigger set-ups and repositioning a wheeled crane would need between panels.
Project data
- Crane: Sennebogen 6113 E telescopic crawler crane
- Project: Haliotis 2 wastewater treatment plant, Nice, France
- Investment: approx. €700m (construction and operation)
- Barrettes: 82 elements over approx. 500 m of dike
- Depth: up to 40 m
- Element size: 6.5–6.6 m wide, 800 mm thick
- Contractor: FAYAT Fondations · Crane supplier: SAML

Related Stories
Raimondi T577 makes UAE debut among 12 flat-tops at Madar Mall
Raimondi Middle East has erected 12 of the 14 flat-top tower cranes in the first tranche for Madar…
Liebherr LTM 1250-5.1 makes its debut beneath Weserstadion roof
Titschkus & Wittrock's new Liebherr LTM 1250-5.1 made its first lift repairing a damaged stand section at Bremen's…
Hoeflon C30e swaps timber for steel beams in German barn job
German dealer Robert Kappel and Baur Minikran used a Hoeflon C30e mini crane with Jib 5 and the…