Ehingen / Donau (Germany) September 2016 – As part of the Stuttgart 21 infrastructure project, a pedestrian bridge had to be removed to be replaced by a new railway bridge in Baden-Württemberg’s state capital. Crane contractor Wiesbauer assembled its Liebherr LG 1750 lattice boom crane on the banks of the River Neckar to remove the wooden bridge. Despite the bridge weight being significantly higher than expected, the crane successfully completed the work.
The most powerful mobile crane in the Wiesbauer crane fleet had been assembled to dismantle the wooden bridge which was installed in 1977. The Liebherr LG 1750 provided sufficient hoisting capacity for this job with its 84-metre main boom and total ballast of 530 tonnes. The larger section of the Neckar bridge, measuring 72 metres in length, was removed.
After taking material samples and examining the design documents, the project planners expected the bridge to have a total weight of 110 tonnes. However, it quickly became clear when the roofed wooden bridge was hoisted that it was significantly heavier than had been calculated. It was not until the display in the crane cabin of the LG 1750 showed a gross load case of 142 tonnes that the feet of the bridge came away from the abutments and river piers. The rest was then easy. The wooden construction was slowly swung over the River Neckar and placed on the bank for final demolition. The weight difference was the result of a large number of gusset plates and iron reinforcements which had been installed.
However, this unexpected increase in the load case did not take the experts from Wiesbauer completely by surprise. Plenty of crane ballast had been transported to the site and the Liebherr 750-tonne lattice boom crane had plenty of lifting capacity in reserve. Ultimately a total of 530 tonnes of counterweights was placed on the turntable and in the derrick boom tray in the 18-metre radius.
The pedestrian bridge over the River Neckar was built for the Federal Garden Show in 1977. When it was opened it was one of the longest roofed wooden bridges in the world. The eastern section of the structure is to be removed over the next few months.

Related Stories
Tadano PM 18 SP loader crane rides a PistenBully at Kronplatz
Ski resort operator Funivie di Valdaora services its tower-mounted snow cannons with a Tadano PM 18 SP knuckle…
Ponticelli MK 88-4.1 repairs JR’s Pont-Neuf artwork in Paris
A Liebherr MK 88-4.1 mobile construction crane from Ponticelli repaired storm damage to artist JR's inflatable installation 'La…
Potain tower cranes build Indonesia’s new presidential palaces
A Potain MC 310 K12 and MC 205 B are erecting the Garuda Palace and State Palace in…