Ehingen / Donau (Germany) September 2016 – As part of the Stuttgart 21 infrastructure project, a pedestrian bridge had to be removed to be replaced by a new railway bridge in Baden-Württemberg’s state capital. Crane contractor Wiesbauer assembled its Liebherr LG 1750 lattice boom crane on the banks of the River Neckar to remove the wooden bridge. Despite the bridge weight being significantly higher than expected, the crane successfully completed the work.
The most powerful mobile crane in the Wiesbauer crane fleet had been assembled to dismantle the wooden bridge which was installed in 1977. The Liebherr LG 1750 provided sufficient hoisting capacity for this job with its 84-metre main boom and total ballast of 530 tonnes. The larger section of the Neckar bridge, measuring 72 metres in length, was removed.
After taking material samples and examining the design documents, the project planners expected the bridge to have a total weight of 110 tonnes. However, it quickly became clear when the roofed wooden bridge was hoisted that it was significantly heavier than had been calculated. It was not until the display in the crane cabin of the LG 1750 showed a gross load case of 142 tonnes that the feet of the bridge came away from the abutments and river piers. The rest was then easy. The wooden construction was slowly swung over the River Neckar and placed on the bank for final demolition. The weight difference was the result of a large number of gusset plates and iron reinforcements which had been installed.
However, this unexpected increase in the load case did not take the experts from Wiesbauer completely by surprise. Plenty of crane ballast had been transported to the site and the Liebherr 750-tonne lattice boom crane had plenty of lifting capacity in reserve. Ultimately a total of 530 tonnes of counterweights was placed on the turntable and in the derrick boom tray in the 18-metre radius.
The pedestrian bridge over the River Neckar was built for the Federal Garden Show in 1977. When it was opened it was one of the longest roofed wooden bridges in the world. The eastern section of the structure is to be removed over the next few months.

Related Stories
Link-Belt TCC-2500 on billion-dollar Puerto Rico flood project
A Link-Belt TCC-2500 telecrawler is tandem-lifting 50,000 lb rebar cages and installing sheet piling on the Rio Puerto…
Zoomlion ZCC6000 crawler crane tackles Indonesian power plant lifts
A 500-tonne Zoomlion ZCC6000 crawler crane with super-lift tower-boom rig is placing 60-tonne boiler drums at an alumina…
Seven Liebherr tower cranes on Ulm’s B10 bridge replacement
ARGE B10 is replacing Ulm's Wallstrassenbruecke with a seven-crane Liebherr concept from Nagel Mietservice, led by two 520…