Ehingen / Donau (Germany) September 2016 – As part of the Stuttgart 21 infrastructure project, a pedestrian bridge had to be removed to be replaced by a new railway bridge in Baden-Württemberg’s state capital. Crane contractor Wiesbauer assembled its Liebherr LG 1750 lattice boom crane on the banks of the River Neckar to remove the wooden bridge. Despite the bridge weight being significantly higher than expected, the crane successfully completed the work.
The most powerful mobile crane in the Wiesbauer crane fleet had been assembled to dismantle the wooden bridge which was installed in 1977. The Liebherr LG 1750 provided sufficient hoisting capacity for this job with its 84-metre main boom and total ballast of 530 tonnes. The larger section of the Neckar bridge, measuring 72 metres in length, was removed.
After taking material samples and examining the design documents, the project planners expected the bridge to have a total weight of 110 tonnes. However, it quickly became clear when the roofed wooden bridge was hoisted that it was significantly heavier than had been calculated. It was not until the display in the crane cabin of the LG 1750 showed a gross load case of 142 tonnes that the feet of the bridge came away from the abutments and river piers. The rest was then easy. The wooden construction was slowly swung over the River Neckar and placed on the bank for final demolition. The weight difference was the result of a large number of gusset plates and iron reinforcements which had been installed.
However, this unexpected increase in the load case did not take the experts from Wiesbauer completely by surprise. Plenty of crane ballast had been transported to the site and the Liebherr 750-tonne lattice boom crane had plenty of lifting capacity in reserve. Ultimately a total of 530 tonnes of counterweights was placed on the turntable and in the derrick boom tray in the 18-metre radius.
The pedestrian bridge over the River Neckar was built for the Federal Garden Show in 1977. When it was opened it was one of the longest roofed wooden bridges in the world. The eastern section of the structure is to be removed over the next few months.

Related Stories
Italy’s first Liebherr Fibre crane builds Val Trompia water plant
Facchetti Costruzioni has put a Liebherr 240 EC-B Fibre to work on the Bovegno drinking water treatment plant…
Pontáns Kranar MK 88-4.1E shifts canopy roof to roof in Uppsala
Squeezed between two six-storey blocks in Uppsala, a Liebherr MK 88-4.1E lifted nearly 20 aluminium canopy segments of…
Pair of Unic URW-706 spider cranes float in to renew canal lock gates
With no road access to the lock, two Unic URW-706 mini spider cranes travelled to site by pontoon…