ALE has loaded-out the Malikai Tension Leg Platform (TLP), weighing 27,500t, at Malaysia Marine and Heavy Engineering (MMHE) West in Johor Darul Takzim, Malaysia. The actual skidding was completed in just 12 hours and it marks another major milestone for Malikai Project.
This load-out was part of the contracted scope of work for the Malikai Project, which was awarded on behalf of TMJV. In July 2015, ALE was responsible for Superlift activities which include weighing the Topside, jacking it up 40m using ALE’s Mega Jack system and skidding it 90m at elevation before mating the Topside with the Hull. Currently, it stands as the world’s highest ever jack-up and skidding operations on this scale.
Subsequently in March 2016, ALE skidded the TLP 75m onto the ‘White Marlin’ vessel using eight strand jacks, with 900t capacity each. Each strand jack was fitted with 39 strand wires, giving a total pulling capacity of 5,928t. As well as the skidding operation for the load-out, ALE operated their barge level monitoring system.
ALE – Offshore Services’ Engineering Manager Barney Mills, who coordinated the load-out operation, commented: “This was a challenging operation as the loadout was undertaken with the vessel in a side-on position. This meant that the control and monitoring of the vessel stability during the load transfer was crucial. Quay jacks were used to ensure the vessel heel remain positive by way of monitoring calculated load on the quay. We also utilised our barge level monitoring system to constantly monitor the vessel trim, heal and deck shape in real time throughout the load-out.”
“We are really proud to be involved in such a landmark and industry-leading project such as this. Our clients have praised us for our smooth execution and professionalism shown throughout the project. As the project completes, I want to thank all of the teams for their hard work in achieving this milestone together.”
The White Marlin has since taken the TLP to an area off the coast of Singapore, where the float-off operation was completed, the TLP towed back and moored against the quay for final testing and commissioning. Once completed, the TLP will be towed to its operating offshore site, 100km from Sabah, Malaysia.

Related Stories
Italy’s first Liebherr Fibre crane builds Val Trompia water plant
Facchetti Costruzioni has put a Liebherr 240 EC-B Fibre to work on the Bovegno drinking water treatment plant…
Pontáns Kranar MK 88-4.1E shifts canopy roof to roof in Uppsala
Squeezed between two six-storey blocks in Uppsala, a Liebherr MK 88-4.1E lifted nearly 20 aluminium canopy segments of…
Pair of Unic URW-706 spider cranes float in to renew canal lock gates
With no road access to the lock, two Unic URW-706 mini spider cranes travelled to site by pontoon…