ALE has successfully completed their first project milestone in a major joint Norwegian/German renewable energy project.
The global heavylift contractor has successfully delivered and installed the first two transformers for the Nordlink Project in Tonstad, Norway.
ALE has been contracted to provide the engineering, heavy transportation and installation of 14 transformers, weighing approximately 225t each. With seven being delivered to Tonstad, Norway, and seven being delivered to Wilster, Germany.
ALE commenced operations in June with the receiving of the transformers at the Port of Kvinesdal and transported them using the AL100 girder frame and 26 axle lines of conventional trailers along a very technically challenging 70km route through the Norwegian mountains.
Andrew Stephens, Technical Sales Manager for ALE, stated: “We are proud to have successfully reached the first critical milestone for the project. Reaching this point is testament to the hard work, effort and dedication by the whole project team to date. It also showcases how we are operating our new locally-based equipment for the project.”
The NordLink project is the first girder frame project to be executed by ALE in Norway utilising its new locally based equipment and operations team. Referred to as the ‘Green Cable’ project, it sees the exchange of renewable energies between the Norwegian and German power grids. The project will allow exchange of renewable energies, especially hydroelectric power and wind power, between both countries. At 623km long, this will be one of the longest high voltage direct current (HVDC) connection in Europe

Related Stories
Link-Belt TCC-2500 on billion-dollar Puerto Rico flood project
A Link-Belt TCC-2500 telecrawler is tandem-lifting 50,000 lb rebar cages and installing sheet piling on the Rio Puerto…
Zoomlion ZCC6000 crawler crane tackles Indonesian power plant lifts
A 500-tonne Zoomlion ZCC6000 crawler crane with super-lift tower-boom rig is placing 60-tonne boiler drums at an alumina…
Seven Liebherr tower cranes on Ulm’s B10 bridge replacement
ARGE B10 is replacing Ulm's Wallstrassenbruecke with a seven-crane Liebherr concept from Nagel Mietservice, led by two 520…