A 275-ton all terrain and a 120-ton telescopic truck crane work in tandem on an ASTEC plant build in eastern Kentucky
American Industrial Contractors used a Link-Belt ATC-3275 all terrain crane and a 120|HT telescopic truck crane in tandem to erect a new ASTEC asphalt plant at a working limestone quarry in Stanton, Kentucky.
Two cranes, one plant
The site at Hinkle Contracting’s Natural Bridge Stone Co. in Stanton, Kentucky, is both a limestone quarry and a hot mix asphalt plant, supplying central and eastern Kentucky. The new ASTEC plant was installed to raise mix production, and American Industrial Contractors of Lexington took on the erection work.
Two Link-Belt machines handled the heavy components: a 275-ton ATC-3275 all terrain crane and a 120-ton 120|HT telescopic truck crane. The pair worked in tandem to lift several of the plant’s large elements into position, including silos and tanks.
Tandem picks on a live quarry
Tandem lifting is the standard answer for tall, slender components such as asphalt silos, where a single hook would leave the load in an unmanageable attitude during the pick. Using two cranes allows the component to be raised from horizontal on a trailer and rotated to vertical under control before it is landed on its foundation.
Photographs of the job show both machines rigged on a prepared concrete pad with a silo section suspended between them, being brought upright over its base. Working on an operating quarry adds the usual constraints of shared haul roads and live production alongside the erection sequence.
Link-Belt has not released the individual component weights, lift radii or the duration of the erection programme.
Cranes
- Model: Link-Belt ATC-3275 all terrain crane, 275 US tons
- Model: Link-Belt 120|HT telescopic truck crane, 120 US tons
- Method: Tandem lifting
Project
- Contractor: American Industrial Contractors, Lexington, Kentucky
- Site: Natural Bridge Stone Co., Stanton, Kentucky
- Owner: Hinkle Contracting
- Scope: Erection of a new ASTEC asphalt plant
- Components lifted: Silos and tanks

Related Stories
Italy’s first Liebherr Fibre crane builds Val Trompia water plant
Facchetti Costruzioni has put a Liebherr 240 EC-B Fibre to work on the Bovegno drinking water treatment plant…
Pontáns Kranar MK 88-4.1E shifts canopy roof to roof in Uppsala
Squeezed between two six-storey blocks in Uppsala, a Liebherr MK 88-4.1E lifted nearly 20 aluminium canopy segments of…
Pair of Unic URW-706 spider cranes float in to renew canal lock gates
With no road access to the lock, two Unic URW-706 mini spider cranes travelled to site by pontoon…