Link-Belt 348 Series 2 sets 84,000 lb precast panels at Publix build

Link-Belt 348 Series 2 crawler crane placing a precast concrete panel at the Publix site in Lexington, Kentucky

One-sided access: Link-Belt 348 Series 2 erects 445 precast panels for multi-level Publix store in Lexington

Precast specialist Wells used a 300 USt Link-Belt 348 Series 2 lattice crawler to erect 445 concrete panels, the heaviest at 84,000 lb fully rigged, for a Publix grocery store stacked above a two-storey parking garage in Lexington, Kentucky.

Link-Belt 348 Series 2 lattice crawler crane of Wells on the confined Chevy Chase jobsite
Aerial view of the Link-Belt 348 Series 2 erecting precast panels above the parking garage levels
The completed precast structure of the multi-level Publix store in Lexington

Working from one side only

The new store is going up on a 1.26-acre parcel in Lexington’s Chevy Chase neighbourhood, with the 40,000 sq ft supermarket sitting on top of a two-storey parking garage. Erection contractor ISHI Precast Erectors of Stone Mountain, Georgia brought in Wells, based in Albany, Minnesota, whose 348 Series 2 handled every panel on the job. It is the first Publix that ISHI has built in Kentucky, after erecting precast stores in Tennessee and Georgia.

The tight urban plot left no room to walk the crane around the structure. Panels weighing up to 30,000 lb were placed at a 130 ft radius, and the heaviest picks came in at 84,000 lb fully rigged.

“The capacity of the Link-Belt helped us carry out the weights well since the access area for this job was so small. This was a challenging job. Normally, you have access all around the building, but we only had access on the northwest side of the property.”

— Carlos Ordonez, Key Principal, ISHI Precast Erectors

Two months of steady panel work

Wells operator Roy Kidd ran the crawler for the two months it spent on site and credits the boom’s capacity with keeping the panel cycle quick on the confined plot. “It makes a big difference to have a stout boom when in tight job site spaces,” he says. “It’s a great-running crane.”

From pick-and-carry duties to self-assembly, Kidd found the 348 Series 2 smooth and operator friendly, and he singled out the cab for long shifts. “I won’t lie to you, I love the seats,” he says. “When you sit in a crane all day, that seat matters.”

Job facts

  • Crane: Link-Belt 348 Series 2 lattice crawler
  • Capacity: 300 USt
  • Panels erected: 445 precast concrete panels
  • Heaviest pick: 84,000 lb fully rigged
  • Working radius: up to 130 ft with 30,000 lb panels
  • Project: 40,000 sq ft Publix store above a two-storey parking garage, Lexington, Kentucky
  • Contractor: ISHI Precast Erectors with Wells
  • Time on site: two months