World’s first Tadano CC 78.1250-1 takes on delicate power station dismantling in Ohio
Maxim Crane Works has deployed the first Tadano CC 78.1250-1 ever delivered on its maiden job: dismantling baghouses of around 230 tonnes perched above a state highway at the decommissioned W.H. Sammis coal-fired power station in Stratton, Ohio.
The 2.2-gigawatt W.H. Sammis station on the Ohio River generated its first power in 1960 and was fully decommissioned in 2023, clearing the way for redevelopment into an energy and data centre campus. B&B Wrecking of Cleveland is bringing down the seven power units, five chimneys and multiple baghouses, mostly by controlled implosion. But several baghouses sit on a tunnel bridge deck running above Ohio Route 7, hemmed in by power lines, waterways and rail infrastructure, and have to be cut at height and lifted down instead.
“This is more of a dismantling than demolition because of the sheer size, weight and stakeholder issues that we could possibly encounter.”
— Bryan Donatelli, onsite project manager, B&B Wrecking
Filling a fleet gap
The crawler cranes of up to 700 tonnes already supplied by Maxim Crane Works lacked the reach and capacity to lift the roughly 230-tonne baghouse sections economically, and B&B initially looked elsewhere. Maxim’s crawler fleet ran from 30 to 2,300 tonnes, but with nothing between 1,000 and 1,300 tonnes. The Wilder, Kentucky-based rental house closed that gap by ordering the 1,250-tonne class CC 78.1250-1 — the first unit of the type delivered anywhere in the world — and shipped it from the port straight to the jobsite.
“Our primary reasons for picking the CC 78.1250-1 were its high capacity, flexibility and easy transport. It was a true partnership between us and Tadano. They helped us land this first job.”
— Dan Murray, VP of crawler cranes, Maxim Crane Works
Despite the jump in size, Maxim needed no new trailers: every component, including the capacity-boosting Boom Booster kit, folds down to fit the company’s existing heavy-haul fleet. Assembly began in early February with four Tadano technicians on site, and the crew beat the agreed erection window by almost a week.
Picks at 90 per cent
For the Sammis lifts the crane was rigged with 74 m of main boom and a 48 m luffing jib, carrying 208 tonnes of main body counterweight plus 20 tonnes of central ballast. The Superlift configuration added a 42 m mast at a 21 m radius with 540 tonnes of counterweight on the Split Tray, whose quick-coupling design lets unneeded counterweight be dropped off quickly after boom assembly.
Working from former chimney foundations, the crane is making around 13 picks per position across three set-up locations. The heaviest lift so far came to roughly 294 tonnes — at 90 per cent of chart in that configuration. Operator Patrick Steiner, new to the IC-1 control system, praised the crane’s precision and the 1.6 m wide S-Pace cab. The CC 78.1250-1 is expected to stay on site for about six months, after which Maxim says demand from refining, petrochemical and steel projects is already queueing up.
Facts
- Crane: Tadano CC 78.1250-1, 1,250 t class lattice boom crawler (first unit worldwide)
- Owner: Maxim Crane Works, Wilder, Kentucky
- Client: B&B Wrecking, Cleveland
- Job: Baghouse dismantling, W.H. Sammis Power Station, Stratton, Ohio
- Rig: 74 m main boom + 48 m luffing jib
- Counterweight: 208 t main body + 20 t central ballast; 540 t Superlift on Split Tray, 42 m mast at 21 m radius
- Heaviest pick: approx. 294 t at 90% of chart
- Max main boom: 209 m
- On site: approx. six months

Related Stories
Liebherr LR 11350 tops out world’s tallest wind turbine in Lusatia
A Schmidbauer-operated Liebherr LR 11350 crawler crane has completed the 365-metre GICON high-altitude wind turbine in Brandenburg, handling…
LTM 1450-8.1 lifts historic suspension railway carriage in Wuppertal
Franz Bracht Kran-Vermietung used a Liebherr LTM 1450-8.1 with reduced outrigger base to place a 1950 suspension railway…
Helicopter lifts Liebherr derrick crane onto Paris high-rise roof
A Liebherr 200 DR 5/10 Litronic derrick crane was flown piece by piece onto the roof of the…