ALE has demonstrated its multi-service and wind-specific capabilities whilst performing the electro-mechanical installation for the Garayalde wind farm project, Argentina.
The global heavylifting contractor was contracted to perform the electro-mechanical installation of seven wind turbine generators (WTGs).
Commencing in January, the components were received at Puerto Madryn. Once on-site 260km away, ALE worked with the crane team to implement the mechanical works and the assembly of the components by their global electro-mechanical installation team. ALE then performed all electrical works and handed over the turbines fully assembled to the client.
Carlos Moreno, Commercial Manager for ALE- Wind Services, explained the benefits of using these specialist teams: “This was the first time we have executed this installation scope in Argentina and it was completed successfully because of our team’s flexibility, local expertise, installation knowledge and specialist equipment.
“This was a complex project, made challenging by its remote location. With the team collaboration between many nationalities such as South African, Argentina, Spanish and Brazilian, our project management skills and installation experts could overcome the challenges and demonstrate our operational flexibility, global management and specialist wind capabilities for this market.”

Related Stories
Italy’s first Liebherr Fibre crane builds Val Trompia water plant
Facchetti Costruzioni has put a Liebherr 240 EC-B Fibre to work on the Bovegno drinking water treatment plant…
Pontáns Kranar MK 88-4.1E shifts canopy roof to roof in Uppsala
Squeezed between two six-storey blocks in Uppsala, a Liebherr MK 88-4.1E lifted nearly 20 aluminium canopy segments of…
Pair of Unic URW-706 spider cranes float in to renew canal lock gates
With no road access to the lock, two Unic URW-706 mini spider cranes travelled to site by pontoon…