Energias de Portugal, the largest electric utility company in the Portugal, has been building the Baixo Sabor hydroelectric plant in the municipality of Torre de Moncorvo. Comprised by two dams, the main one is located upstream of the Sabor River and set 9.5 kilometers apart from the downstream one, that will flood an area over 50 km.
The jobsite employs up to 1675 people, with an excavation volume of around 3,000,000 m3, where a volume of 1,100,000 m3 concrete shall be used. The magnitude of the project also requires a large amount of machinery. Therefore, Ibergru has supplied 15 Linden Comansa cranes to the jobsite. The flat-top tower cranes have a maximum load in a range between 5 and 48 tons.
[nggallery id=2]

Related Stories
Hoeflon minis move angel statues in Barcelona Cathedral crypt
Transgruas Salavedra used an electric Hoeflon C30e and C1e to remove and reposition angel statues during restoration work…
Hoeflon C30eL covers college site from one position in Doetinchem
Admiraal Compact deployed a long-boom Hoeflon C30eL at Graafschap College in Doetinchem, covering a large work area from…
Link-Belt TCC-1200 handles steel on Ohio bridge replacement
A rented Link-Belt TCC-1200 telescopic crawler is supporting demolition and placing new steel girders on the US 52…