Energias de Portugal, the largest electric utility company in the Portugal, has been building the Baixo Sabor hydroelectric plant in the municipality of Torre de Moncorvo. Comprised by two dams, the main one is located upstream of the Sabor River and set 9.5 kilometers apart from the downstream one, that will flood an area over 50 km.
The jobsite employs up to 1675 people, with an excavation volume of around 3,000,000 m3, where a volume of 1,100,000 m3 concrete shall be used. The magnitude of the project also requires a large amount of machinery. Therefore, Ibergru has supplied 15 Linden Comansa cranes to the jobsite. The flat-top tower cranes have a maximum load in a range between 5 and 48 tons.
[nggallery id=2]

Related Stories
Helicopter lifts Liebherr derrick crane onto Paris high-rise roof
A Liebherr 200 DR 5/10 Litronic derrick crane was flown piece by piece onto the roof of the…
Tadano ATF 100G-4 lifts 2.5-tonne Bullhead at Wacken Open Air
Crane rental firm Wilhelm used its Tadano ATF 100G-4 to hoist the 2.5-tonne Bullhead skull onto the main…
Seven jobs that show the range of Liebherr Tower Crane Solutions
From a luffing jib crane above the Sagrada Familia to rail-mounted flat-tops at Santiago airport and more than…